Re: NISA - Nuclear and Industrial Safety Agency Press Releases
March 31, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 64th Release)
(As of 08:30 March 31st, 2011)
Major updates are as follows.
Fukushima Dai-ichi NPS
- As the malfunction of the temporary motor-driven pump, which had been
injecting to the Spent Fuel Pool of Unit 2 since 09:25 March 30th, was
confirmed at 09:45 March 30th, the injection pump was switched to the
Fire Pump Truck. However, because cracks were confirmed in the hose
(12:47 and 13:10 March 30th), the injection was suspended. The injection
of fresh water resumed at 19:05 March 30th. (Till 23:50 March 30th)
- In order to prepare for transfer the stagnant water on the basement floor
of turbine building of Unit 2 to the Condenser, the water in the
Condensate Storage Tank is being transferred to the Surge Tank of
Suppression Pool Water. (From 16:45 March 29th)
- In order to prepare for transfer the stagnant water on the basement floor
of turbine building of Unit 3 to the Condenser, the water in the
Condensate Storage Tank is being transferred to the Surge Tank of
Suppression Pool Water. (From 17:40 March 28th)
- Spray of fresh water (Around 140t) over the Spent Fuel Pool of Unit 4
using Concrete Pump Truck was carried out. (From 14:04 till 18:33 March
30th)
- On March 28th, the stagnant water was confirmed in the Main Building
of Radioactive Waste Treatment Facilities. As the result of analysis of
radioactivity, the total amount of the radioactivity 1.2?10^1 Bq/cm3 in the
controlled area and that of 2.2?101 Bq/cm3 in the noncontrolled area were
detected in March 29th.
Fukushima Dai-ni NPS
- Around 17:56 March 30th, a smoke was rising from the power
distribution panel on the first floor of the turbine building of Unit 1.
However, when the power supply was turned off, the smoke stopped to
generate. It was judged by the fire station at 19:15 that this event was
caused by the malfunction of the power distribution panel and was not a
fire.
- The Residual Heat Removal System (B) to cool the reactor of Unit 1
became to be able to receive power from the emergency power supply as
well as the external power supply. This resulted in securing the backup
power supplies (emergency power supplies) of Residual Heat Removal
System (B) for all Units. (14:30 March 30th)
2. Action taken by NISA
(March 29th)
- The "Team to Assist the Lives of the Nuclear Accident Sufferers"
established to strengthen the system to assist the nuclear accident
sufferers carried out visits etc. to relevant cities, towns and villages.
...
http://www.nisa.meti.go.jp/english/files/en20110401-1-1.pdf
March 31, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 64th Release)
(As of 08:30 March 31st, 2011)
Major updates are as follows.
Fukushima Dai-ichi NPS
- As the malfunction of the temporary motor-driven pump, which had been
injecting to the Spent Fuel Pool of Unit 2 since 09:25 March 30th, was
confirmed at 09:45 March 30th, the injection pump was switched to the
Fire Pump Truck. However, because cracks were confirmed in the hose
(12:47 and 13:10 March 30th), the injection was suspended. The injection
of fresh water resumed at 19:05 March 30th. (Till 23:50 March 30th)
- In order to prepare for transfer the stagnant water on the basement floor
of turbine building of Unit 2 to the Condenser, the water in the
Condensate Storage Tank is being transferred to the Surge Tank of
Suppression Pool Water. (From 16:45 March 29th)
- In order to prepare for transfer the stagnant water on the basement floor
of turbine building of Unit 3 to the Condenser, the water in the
Condensate Storage Tank is being transferred to the Surge Tank of
Suppression Pool Water. (From 17:40 March 28th)
- Spray of fresh water (Around 140t) over the Spent Fuel Pool of Unit 4
using Concrete Pump Truck was carried out. (From 14:04 till 18:33 March
30th)
- On March 28th, the stagnant water was confirmed in the Main Building
of Radioactive Waste Treatment Facilities. As the result of analysis of
radioactivity, the total amount of the radioactivity 1.2?10^1 Bq/cm3 in the
controlled area and that of 2.2?101 Bq/cm3 in the noncontrolled area were
detected in March 29th.
Fukushima Dai-ni NPS
- Around 17:56 March 30th, a smoke was rising from the power
distribution panel on the first floor of the turbine building of Unit 1.
However, when the power supply was turned off, the smoke stopped to
generate. It was judged by the fire station at 19:15 that this event was
caused by the malfunction of the power distribution panel and was not a
fire.
- The Residual Heat Removal System (B) to cool the reactor of Unit 1
became to be able to receive power from the emergency power supply as
well as the external power supply. This resulted in securing the backup
power supplies (emergency power supplies) of Residual Heat Removal
System (B) for all Units. (14:30 March 30th)
2. Action taken by NISA
(March 29th)
- The "Team to Assist the Lives of the Nuclear Accident Sufferers"
established to strengthen the system to assist the nuclear accident
sufferers carried out visits etc. to relevant cities, towns and villages.
...
http://www.nisa.meti.go.jp/english/files/en20110401-1-1.pdf