• FluTrackers.com Inc. does not provide medical advice. Information on this web site is collected from various internet resources, and the FluTrackers board of directors makes no warranty to the safety, efficacy, correctness or completeness of the information posted on this site by any author or poster. The information collated here is for instructional and/or discussion purposes only and is NOT intended to diagnose or treat any disease, illness, or other medical condition. Every individual reader or poster should seek advice from their personal physician/healthcare practitioner before considering or using any interventions that are discussed on this website. By continuing to access this website you agree to consult your personal physican before using any interventions posted on this website, and you agree to hold harmless FluTrackers.com Inc., the board of directors, the members, and all authors and posters for any effects from use of any medication, supplement, vitamin or other substance, device, intervention, etc. mentioned in posts on this website, or other internet venues referenced in posts on this website.
  • We are not asking for any donations. Do not donate to any entity who says they are raising funds for us.

NISA - Nuclear and Industrial Safety Agency Press Releases

Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 21, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 40th Release)
(As of 21:00 March 21st, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPS)
 Fukushima Dai-ichi NPS
・ White smoke generated from Unit 2 (18:22 March 21st).
・ Grayish smoke generated from Unit 3 (At around 15:55 March 21st). Thereafter the smoke was confirmed to be died down (17:55 March 21st).

...

http://www.nisa.meti.go.jp/english/files/en20110322-1-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 21, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 41th Release)
(As of 07:30 March 22nd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
< Situation of Water Spray >
・ Injection of Water to Common Spent Fuel Pool was finished. (From 10:37
till 15:30 March 21st). Water temperature of the pool was around 61 ℃
(16:30 March 21st).

< Directives by Nuclear Emergency Response Headquarters >
・ On March 21st, the Directive regarding foods and drinks was issued to
the Prefectural Governors of Fukushima, Ibaraki, Tochigi and Gunma,
which directs those governors to issue a request for relevant businesses
and people to suspend shipment of the following products for the time
being;
① Spinach and Kakina (a green vegetable) produced in Fukushima,
Ibaraki, Tochigi and Gunma Prefectures
② Raw milk produced in Fukushima Prefecture
・ At 16:45 March 21st, the Directive titled as ?Ventilation for using
heating equipments within the in-house evacuation zone? was issued to
the Prefectural governor and the heads of cities, towns and villages
(Tomioka Town, Hutaba Town, Okuma Town, Namie Town, Kawauchi
Village, Naraha Town, Minamisouma City, Tamura City, Kazurao
Village, Hirono Town, Iwaki City and Iidate Village), which directs the
above-mentioned governor and heads to publicly announce the guidance
to the residents within the in-house evacuation zone, concerning the
indoor use of heating equipments that require ventilation, from the
viewpoints of prevention from carbon monoxide poisoning and to
reducing exposure.
...
http://www.nisa.meti.go.jp/english/files/en20110322-2-1.pdf


March 22, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 42th Release)
(As of 12:30 March 22nd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
<State of Smoke>
・ White smoke generated at 18:22 March 21st was died down and almost
invisible. (As of 07:11 March 22nd)
・ Grayish smoke generated around 15:55 March 21st changed to be
whitish and seems to be ceasing. (As of 07:11 March 22nd)
...

http://www.nisa.meti.go.jp/english/files/en20110322-3-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 22, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 43rd Release)
(As of 18:00 March 22nd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
< Situation of Water Injection and Water Spray >
・ Injection of 18t of Seawater to the Spent Fuel Pool of Unit 2 was carried out. (from 16:07 till 17:01 March 22nd)
・ Water spray over Unit 3 by Hyper Rescue Unit of Tokyo Fire Department was carried out. (from 15:10 till 15:59 March 22nd)
・ Water spray over Unit 4 using a Concrete Pump Truck (50t/h) was started. (The duration of water spray is scheduled to be 3 hours) (17:17 March 22nd)

...

http://www.nisa.meti.go.jp/english/files/en20110322-4-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

(edited)

March 23, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 44th Release)
(As of 08:00 March 23rd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS

<Situation of Water Injection and Water Spray>
・ Spray of around 180 t of water for Unit 3 by Hyper Rescue
Unit of Tokyo Fire Department was carried out. (from 15:10 till 15:59
March 22nd)
・ Spray of around 150 t of water for Unit 4 using a Concrete
Pump Truck (50t/h) was started. (from 17:17 till 20:32 March 22nd)
・ The amount of injected water to the
Reactor Core of Unit 1 was increased by utilizing water supply line in addition to the Fire Extinguish
Line (2m3/h→18m3/h).(02:33 March 23rd)

<Situation of Power Supply>
・ Power supply to Unit 6 was switched from the Emergency Diesel
Generator to external power supply (19:17 March 22nd)
・ On the side of Unit 3, lighting in the Central Operation
Room of Units 3 and 4 was recovered. (22:43 March
22nd)

http://www.nisa.meti.go.jp/english/files/en20110323-2-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 23, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 45th Release)
(As of 12:30 March 23rd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
<Situation of Water Injection and Water Spray>
・ Water spray using Concrete Pump Truck (50t/h) to the Unit 4 was started.
(10:00 March 23rd)

...

http://www.nisa.meti.go.jp/english/files/en20110323-3-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 23, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 46th Release)
(As of 19:00 March 23rd, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
<Situation of Water Injection and Water Spray>
・ Spray of around 130 t of water for Unit 4 by Concrete Pomp Truck (50t/h) was carried out. (From 10:00 till 13:02 March 23rd)
・ Injection of 35 t of seawater to the Spent Fuel Pool of Unit 3 via the Cooling and Purification Line was carried out. (From 11:03 till 13:20 March 23rd)
・ Slightly blackish smoke generated from the reactor building of Unit 3. (Around 16:20 March 23rd)
< Fire Bureaus? Activities>
・ From 8:30 till 9:30, and from 13:30 till 14:30 on March 23rd, Niigata City Fire Bureau and Hamamatsu City Fire Bureau gave guidance to TEPCO as to the operation of large decontamination system.

...

http://www.nisa.meti.go.jp/english/files/en20110323-4-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 24, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 47th Release)
(As of 08:00 March 24th, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS

<Situation of Water Injection and Water Spray>
・ At around 23:30 March 23rd and around 4:50 March 24th, it was reported
that the smoke generated from the reactor building of Unit 3 seemed to
cease.
・ Seawater injection to the Spent Fuel Pool of Unit 3 via the Cooling and
Purification Line was started. (Around 5:35 March 24th)
・ The pumps for Residual Heat Removal was automatically stopped when
the power supply was switched from the temporary to the permanent.
(17:24 March 23rd)

< Possibility on radiation exposure>
・ Fukushima Prefecture is carrying out the screening at 14 places (set up
permanently) such as health offices. Up until March 21st, the screening
was done to 75,429 people. Among them, 97 people were above the
100,000cpm, but when measured these people again without clothes, etc.,
the counts decreased to 100,000cpm and below.

...

http://www.nisa.meti.go.jp/english/files/en20110324-1-1.pdf


1
March 24, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 48th Release)
(As of 12:30 March 24th, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・ Lighting in the Central Operation Room of Unit 1 was recovered. (11:30
March 24th)
・ Seawater injection to the Spent Fuel Pool of Unit 3 via the Cooling and
Purification Line was started, (Around 5:35 March 24th) and 4~5t of
seawater was confirmed to be injected. (12:08 March 24th)

http://www.nisa.meti.go.jp/english/files/en20110324-2-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 24, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 49th Release)
(As of 19:30 March 24th, 2011)

Major updates are as follows.

1. Exposure of Workers
As for the workers conducting operations in Fukushima Dai-ichi Nuclear Power Station(NPS), the number of people who were at the level of exposure more than 100mSv was 14 (All the people were TEPCO?s employees.), as of the morning of March 24th. Furthermore, today, three workers (All the people were the subcontractor?s employees.) who were laying cables in the turbine building of Unit 3 of the NPS were confirmed to be at the level of exposure more than 170mSv. In total, the number of workers who were at the level of exposure more than 100mSv becomes 17.

2. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・ Around 120t of seawater was injected to the Spent Fuel Pool of Unit 3 via the Cooling and Purification Line. (From around 5:35 till around 16:05 March 24th)
・ Around 150t of seawater was sprayed over the Spent Fuel Pool of Unit 4 using Concrete Pump Truck (50t/h). (From 14:36 till 17:30 March 24th)
・ Repair of the temporary pump for Residual Heat Removal Seawater System for Unit 5 was completed (16:14 March 24th) and cooling was started again. (16:35 March 24th)
・ For the Common Spent Fuel Pool, the external power was started to be supplied, (15:37 March 24th) and cooling was also started.(18:05 March
24th)

...

http://www.nisa.meti.go.jp/english/files/en20110325-1-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

The English translations are running behind, here's the machine translated versions.

Earthquake Information (Part 50)
08:00 March 25th

Changes from the previous below.

1. Employee exposure and
March 24, in the basement and first floor of the turbine building No. 3, three workers had been working cabling (employees work for all) for about 170mSv check the dose of more than about two of the feet confirmed the attachment of radioactive material into the skin. For these two, since it was determined that the possibility of beta radiation burns, Fukushima Medical University Hospital and transported to the scheduled departure of Radiological Sciences in Chiba Prefecture, 25 am today.
In addition, we investigated the workers 踏Mi入Reta Wed, water surface dose rate is about 400mSv / h, gamma-ray nuclide analysis of collected water, the concentration of each sample a total of approximately 3.9 ? 10^6Bq/cm3 a nuclide or.

2. Responses, such as NISA
Nuclear Safety Agency, for the Tokyo Electric Power Company concerning the exposure of workers in the Unit 3 turbine building Fukushima Daiichi Nuclear Power Station that occurred on March 24, in terms of relapse prevention, management reviewed the radiation immediately to improve, verbal instructions.

3. Information from local nuclear emergency response headquarters
March 24, in the next two places near the indoors evacuation was carried out inspections of the thyroid gland in children.
Kawamata Town - Health Center (Fukushima Daiichi Nuclear Power Station 40 ~ 50km zone)
Kawamata Town - 山木屋 Branch (Fukushima Daiichi Nuclear Power Station 30 ~ 40km zone)
[Measured]
- Infants (age 1 to 6) dose of 14 persons including 66 children,
No different from any background and, in light of the Nuclear Safety Commission's approach
Ness level is no problem with it. However, the actual dose of iodine are all
None.

4. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
? The spent fuel pool at Unit 4, start of infusion water purification system for cooling (25 06:05)
1,2,4 - The Unit confirmed that the white smoke continues (06:20 25 days)

...
http://www.meti.go.jp/press/20110325005/20110325005-1.pdf

Earthquake Information (Part 51)
(currently at 12.30 on March 25)

1. Employee exposure and
March 24, in the basement and first floor of the turbine building No. 3, three workers had been working cabling (employees work for all) for about 170mSv check the dose of more than about two of its legs Confirmed the attachment of radioactive material into the skin. For these two, since it was determined that the possibility of beta radiation burns, Fukushima Medical University Hospital, transported to the departure of Radiological Sciences in Chiba Prefecture in the afternoon on the 25th day.
In addition, we investigated the workers 踏Mi入Reta Wed, water surface dose rate is about 400mSv / h, gamma-ray nuclide analysis of collected water, the concentration of each sample a total of approximately 3.9 ? 106Bq/cm3 a nuclide Or.

2. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
? The spent fuel pool at Unit 4, injection of seawater cooling system for the spent fuel pool (Sun 25 06:05 to 10:20)
- Unit 2 spent fuel pool, water injection for the spent fuel pool cooling system (25, 10:30 to 12:19)

3. Industrial Safety Relationship
See Appendix

...

http://www.meti.go.jp/press/20110325006/20110325006-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

English versions of 50 and 51;

Seismic Damage Information (the 50th Release)
(As of 08:00 March 25th, 2011)

Major updates are as follows.

1. Exposure of Workers
On March 24th, three workers (All the people were the subcontractor?s
employees.) who were laying cables on the ground floor and the basement
floor of the turbine building of Unit 3 were confirmed to be at the level of
exposure more than 170mSv. Regarding the two of them, the attachment
of radioactive material on the skin of both legs was confirmed. As the two
workers were judged to have a possibility of beta ray burn, they were
transferred to the Fukushima Medical University Hospital, and are to
depart for the National Institute of Radiological Science in the Chiba
Prefecture in the morning of March 25th.
Concerning the result of survey for the water that those workers
stepped in, the dose rate on the surface of the water was about 400mSv/h
and, as a result of gamma ray nuclide analysis of sampled water, the
concentration of radioactive nuclide of the sample was about 3.9?106
Bq/cm3 in total of each nuclides.

2. Action taken by NISA and other agencies
NISA directed orally to the TEPCO regarding the exposure of workers
at the turbine building of Unit 3 of Fukushima Dai-ichi Nuclear Power
Station occurred on March 24th, to review immediately and to improve its
radiation control measures from the viewpoint of preventing a recurrence.

3. Notice of the Local Emergency Response Headquarters
On March 24th, examinations of thyroid gland for children were carried
out at the following two clinics near the in-house evacuation area.
・ Kawamata Town Health Center (within the area from 40km to 50km
distance from Fukushima Dai-ichi NPS)
・ Kawamata Town Yamakiya Branch Office (within the area from 30km to
40km distance from Fukushima Dai-ichi NPS)

[Result of the Examinations]
・ The dose rate of all the 66 children including 14 infants from 1 to 6 years
old) had no big difference from the level of the background and was at the
level of no problem in light of the view of Nuclear Safety Commission.
For all of them, there was no administration of stable Iodine as actual
result.

4. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・ Seawater injection to the Spent Fuel Pool of Unit 4 via the Cooling and
Purification Line was started. (06:05 March 25th)
・ White smoke was confirmed to generate continuously from Units 1, 2 and
4. (Around 06:20 March 25th)

...

http://www.nisa.meti.go.jp/english/files/en20110325-2-1.pdf

Seismic Damage Information (the 51st Release)
(As of 12:30 March 25th, 2011)

Major updates are as follows.

1. Exposure of Workers
On March 24th, three workers (All the people were the subcontractor?s
employees.) who were laying cables on the ground floor and the basement
floor of the turbine building of Unit 3 were confirmed to be at the level of
exposure more than 170mSv. Regarding the two of them, the attachment
of radioactive material on the skin of both legs was confirmed. As the two
workers were judged to have a possibility of beta ray burn, they were
transferred to the Fukushima Medical University Hospital, and departed
for the National Institute of Radiological Sciences in the Chiba Prefecture
in the afternoon of March 25th.
Concerning the result of survey for the water that those workers
stepped in, the dose rate on the surface of the water was about 400mSv/h
and, as a result of gamma ray nuclide analysis of sampled water, the
concentration of radioactive nuclide of the sample was about 3.9?106
Bq/cm3 in total of each nuclides.

2. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・ Injection of seawater to the Spent Fuel Pool of Unit 4 via the Fuel Pool
Cooling Line was carried out. (From 06:05 till 10:20 March 25th)
・ Injection of seawater to the Spent Fuel Pool of Unit 2 via the Fuel Pool
Cooling Line was carried out. (From 10:30 till 12:19 March 25th)

...

http://www.nisa.meti.go.jp/english/files/en20110325-3-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 25, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 52nd Release)
(As of 19:30 March 25th, 2011)

Major updates are as follows.
1. Exposure of Workers
On March 24th, three workers (All the people were the subcontractor?s employees.) who were laying cables on the ground floor and the basement floor of the turbine building of Unit 3 were confirmed to be at the level of exposure more than 170mSv. Regarding the two of them, the attachment of radioactive material on the skin of both legs was confirmed. As the two workers were judged to have a possibility of beta ray burn, they were transferred to the Fukushima Medical University Hospital, and at 16:44 March 25th, all of the three workers arrived at the National Institute of Radiological Sciences in the Chiba Prefecture. The three workers had no serious problem in the condition of the whole body, were fully conscious and ambulatory. Currently, they are being examined concerning exposed dose and so on.
Concerning the result of survey for the water that those workers stepped in, the dose rate on the surface of the water was about 400mSv/h and, as a result of gamma ray nuclide analysis of sampled water, the
concentration of radioactive nuclide of the sample was about 3.9?10^6 Bq/cm3 in total of each nuclides.

2. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・ Injection of fresh water to the Reactor Pressure Vessel of Unit 1 was
started. (15:37 March 25th)
・ Water spray for Unit 3 by Kawasaki City Fire Bureau supported by Tokyo Fire Department was carried out. (From 13:28 till 16:00 March 25th)
・ Injection of fresh water to the Reactor Pressure Vessel of Unit 3 was started. (18:02 March 25th)
・ Water spray for Unit 4 using Concrete Pump Truck (50t/h) was started. (19:05 March 25th)
・ Power supply for the temporary pump for Residual Heat Removal Seawater System (RHRS) of Unit 6 was switched from the temporary to the permanent. (15:38 and 15:42 March 25th)

...

http://www.nisa.meti.go.jp/english/files/en20110325-5-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

Latest updates (Machine translated - I'll add the english versions once they become available)

Earthquake Information (Part 53)
(currently March 26, 8:00)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
- underground reservoir of water was measured turbine building, as the main radionuclide 131I (iodine) is 2.1 × 10^5Bq/cm3, 137Cs (cesium) is 1.8 × 10^6 Bq/cm3, were detected.
Radionuclide analysis of sea water - near the southern outlet, I-131 (iodine) is 5.0 × 10^1Bq/cm3, (water levels outside the limits of 1250.8 times the monitoring area) were detected (for more information as Appendix).
2. Industrial Safety Relationship
See Appendix
3. Responses, such as NISA
<the possibility of employee exposure, such as>
Of the three workers went to work laying cables, and two were confirmed adherence to the skin of the feet of radioactive materials, test results, radiation exposure of the two legs are estimated to be 2 ~ 6Sv, Level of treatment is not needed in both legs and internal exposure was in the hospital to see the progress.
<directions to the food and drink>
Additional information relating to drinking water and limit intake 及 restricted item shipping restrictions

...

http://www.meti.go.jp/press/20110326002/20110326002-1.pdf

Earthquake Information (Part 54)
(currently March 26, 12:00)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
- Start fresh water injection into the reactor pressure vessel of Unit 2 (26 10:10)
2. Industrial Safety Relationship
See Appendix
3. Responses, such as NISA
<directions to the food and drink>
Information relating to the drinking water limit (water supply project that will continue to support) to add

...
http://www.meti.go.jp/press/20110326003/20110326003-1.pdf

53rd release (english) http://www.nisa.meti.go.jp/english/files/en20110326-1-1.pdf

54th release (english) http://www.nisa.meti.go.jp/english/files/en20110326-2-1.pdf
 
Last edited:
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

The following is from Friday’s UCS press briefing and may help with understanding some of the readings. It stems from the first part of the question which – to paraphrase – asked ‘If we have been pumping water into these containments for nearly two weeks why aren’t they filling up?’. All the daily briefings and Q&A’s can be found here. It has been confusing me for a while why one of the pressure readings in reactor 3 has been about a tenth of one Atm, when reading the pressures it may be helpful to remember that normal atmospheric pressure is about 0.1MPa.

REPORTER: I think for the first several days, I think I was under the assumption that they actually didn't have any idea [relating to water pressure and level readings in the NISA reports], and that some of those numbers were assumptions, but they put out new numbers every single day, and they do change, which indicates that they are at least attempting to measure them, but it doesn't make any sense, given the thousands and thousands of tons of water that they've poured in that they haven't apparently made any progress in covering the fuel.

MR. LOCHBAUM: Well, one of the challenges that was identified some 20 years ago, by a colleague of mine, Paul Blanch in Connecticut, was that the water level instrumentation for boiling water reactors is tenuous at best. It's not that you have, like, a level gauge that tells you that you've got X number of inches, or millimeters of level in the reactor vessel.
In a boiling water reactor, when the plant is operating, the water level is boiling, that's where it came from, from its name. So, the way they infer what water level is, is they compare the density or the weight of the water drawn from a sample of the reactor to a reference leg that's not boiling, and when the boiled water boils or the water level drops in the reactor vessel, there's a relative change in that weight versus the weight at the constant level reference leg.
It works fine when the plant is operating normally, but in accident conditions, the heat inside the dry well will boil off the water in the reference leg, which could make your indicated water level 16 feet different from what it really is.
So, attempts have been made to make the water level instrumentation more reliable, we may learn from this that those attempts fixed yesterday's problem but not the one we're facing today. So, that could explain why even though they're getting water level instrumentation, it has no reference to reality.

REPORTER: Would that be your best guess is that these levels actually are fairly meaningless?

MR. LOCHBAUM: Well, they're reporting two different levels, an A and a B for most of the reactors on Unit 3, they're saying the A and the C. There are three different water level instruments, that's the A, B and the C channels, and typically if you see a problem like I just described you would see one of them go off first, because they don't all react that same way because they're located physically in different places.
So far, they've been hanging in pretty close. One might say 1740 millimeters and the other is 1750. If you started seeing those kind of casually, you might start seeing one go either up or down and the other one hanging there like it was yesterday. So, we're not seeing those aberrations. So, it's not much more than a guess, based on the data, because the instrumentation may be suspect, so the values we're getting may or may not reflect reality. So, I think they're faced with that problem and we are as well.

REPORTER: Okay, thanks.
 
Re: METI - Fukushima Dai-ichi reactor readings spreadsheets

Re: METI - Fukushima Dai-ichi reactor readings spreadsheets

machine translation

Earthquake Information (Part 55)
(currently March 26, 18:30)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
Return the main control room lighting - Unit 2 (26 16:46)
2. Industrial Safety Relationship
See Appendix

...

http://www.meti.go.jp/press/20110326005/20110326005-1.pdf

english release 55 http://www.nisa.meti.go.jp/english/files/en20110326-3-1.pdf
english release 56 http://www.nisa.meti.go.jp/english/files/en20110327-1-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

Japanese to English translation
Earthquake Information (Part 57)
(currently 3:30 pm on March 27)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
• For Unit 3, concrete pump trucks (50t / h) the discharge
(Sun 27 12:34 to 14:36​​)
Radionuclide analysis of sea water - near the southern outlet, 131I (iodine) is 7.4 × 101Bq/cm3
(limit of water concentration outside the monitoring area of 1850.5-fold) was detected. (26 14:30)
...

http://www.meti.go.jp/press/20110327002/20110327002-1.pdf

english release 57 http://www.nisa.meti.go.jp/english/files/en20110327-2-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

Japanese to English translation
Earthquake Information (Part 58)
(Currently 00 minutes at the 8th March 28)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
- No. 2 on the switch to an electric pump to a temporary injection of fresh water reactor pressure vessel due to fire pump (27 18:31)
For Unit 2 - Tokyo Electric Power, March 27 (Co) for measurement of water reservoir Unit 2 turbine building basement Fukushima Daiichi Nuclear Power Station was announced, the decision is wrong with the measurement of iodine-134 Sampling and analysis of the results of re-evaluation based on the concentration of gamma radionuclides including iodine-134 is reported to be less than the detection limit. (0:07, 28)
- The Nuclear Safety Agency for TEPCO, for errors relating to evaluate this measure, aimed at preventing the recurrence of such instructions orally.
? For Unit 4, concrete pump trucks (50t / h) the discharge
Radionuclide analysis of sea water - near the southern outlet, 131I (iodine) is 7.4 ? 101Bq/cm3 (limit of water concentration outside the monitoring area of ​​1850.5-fold) was detected. (26 14:30)
(Measured results on March 27 was 250 times the water concentration limits. (27th 13:50), while, 1F nuclide analysis of the North Sea outlet, 131I (iodine) is 4.6 ? 101Bq/cm3 (The 1,150-fold) was detected. (27th 14:05))

...
http://www.meti.go.jp/press/20110328003/20110328003-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

Japanese to English translation
Earthquake Information (Part 59)
(Current 15:00, 28 March)

Changes from the previous below.
1. Related nuclear power plant
○ Fukushima Daiichi Nuclear Power Station
2. Industrial Safety Relationship
See Appendix
3. Responses, such as NISA
[March 28]
13:50 Nuclear Safety Agency, the Nuclear Safety Commission advises special meeting (on water retention in the turbine building basement Fukushima Daiichi Power Station Unit 2) by a Tokyo Electric Power Company for additional water monitoring points Implementation of groundwater monitoring, and verbal instructions.
<The possibility of exposure (exposure of employees and other)>
Three employees had been hospitalized for 24 days Fukushima Medical University Hospital, all three were discharged around noon Thursday.

...

http://www.meti.go.jp/press/20110328008/20110328008.html
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 29, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 60th Release)
(As of 08:00 March 29th, 2011)

1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・The water was confirmed to be collected in the vertical parts of the trenches
(an underground structure for laying pipes, shaped like a tunnel) outside
of the turbine building of Units 1 to 3. The dose rates on the water surface
were 0.4 mSv/h of the Unit 1?s trench and 1,000 mSv/h of the Unit 2?s
trench. The rate of the Unit 3?s trench could not measure because of the
rubble. (Around 15:30 March 27th)
・The pump for the fresh water injection to RPV of Unit 3 was switched from
the Fire Pump Truck to the temporary motor-driven pump.(20:30 March
28th)
・In the samples of soil collected on 21 and 22 March 2011 on the site (at 5
points) of Fukushima Dai-ichi NPS, plutonium 238, 239 and 240 were
detected (23:45 March 28th announced by TEPCO). The concentration of
the detected plutonium was at the equivalent level of the fallout
(radioactive fallout) that was observed in Japan concerning the past
atmospheric nuclear testing, i.e. at the equivalent level of the normal
condition of environment, and was not at the level of having harmful
influence on human body.
2. Action taken by NISA
(March 28th)
Regarding the delay in the reporting of the water confirmed outside of
the turbine buildings, NISA directed TEPCO to accomplish the
communication in the company on significant information in a timely
manner and to inform it in a timely and appropriate manner.

...

http://www.nisa.meti.go.jp/english/files/en20110329-7-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 29, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 61st Release)
(As of 15:00 March 29th, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
・The pump for the fresh water injection to RPV of Unit 1 was switched from
the Fire Pump Truck to the temporary motor-driven pump.(08:32 March
29th)
・Water spray (fresh water) for Unit 3 using Concrete Pump Truck (50t/h)
was started. (14:17 March 29th)
・Lighting of Central Operation Room of Unit 4 was recovered (11:50 March
29th)
・When removing the flange of pipes of Residual Heat Removal Seawater
System outside the building of Unit 3, three subcontractor?s employees
were wetted by the water remaining in the pipe. However, as the result of
wiping the water off, no radioactive materials were attached to their
bodies.

2. Action taken by NISA
・On March 28th, Chief Cabinet Secretary mentioned the continuation of the
limited-access within the area of 20 km from Fukushima Dai-ichi NPS. On
the same day, the Local Emergency Response Headquarters notified the
related municipalities of forbidding entry to the evacuation area within
the 20 km zone.
・The report was received, regarding the accident and trouble etc. in
Onagawa NPS of Tohoku Electric Power Co. Inc. (the trouble of pump of
component cooling water system etc. in Unit 2 and the fall of heavy oil
tank for auxiliary boiler of Unit 1 by tsunami), pursuant to the Article 62-3
of the Nuclear Regulation Act and the Article 3 of the Ministerial
Ordinance for the Report Related to Electricity. (11:16 March 29th)

...

http://www.nisa.meti.go.jp/english/files/en20110330-1-1.pdf
 
Re: NISA - Nuclear and Industrial Safety Agency Press Releases

March 30, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 62nd Release)
(As of 08:00 March 30th, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
㋪The seawater injection to the Spent Fuel Pool of Unit 2 using the Fire Pump
Truck was switched to the freshwater injection using the temporary
motor-driven pump. (From 16:30 till 18:25 March 29th)

...

http://www.nisa.meti.go.jp/english/files/en20110331-1-1.pdf

1
March 30, 2011
Nuclear and Industrial Safety Agency
Seismic Damage Information (the 63rd Release)
(As of 15:30 March 30th, 2011)

Major updates are as follows.
1. Nuclear Power Stations (NPSs)
 Fukushima Dai-ichi NPS
㋪As the Condenser of Unit 1 was confirmed to be almost filled with water,
pumping out of the water to the Condenser was stopped. (07:30 March
29th)
㋪As the malfunction of temporary motor-driven pump injecting to the Spent
Fuel Pool of Unit 2 was confirmed to be in a bad condition, the injection
pump was switched to the Fire Pump Truck. However, because cracks were
confirmed in the hose (12:47 and 13:10 March 30th), the injection was
currently being suspended.
㋪Freshwater injection to the Spent Fuel Pool of Unit 4 using Concrete Pump
Truck was started. (14:04 March 30th)
2. Action taken by NISA
㋪Directions as to implement the emergency safety measures for the other
power stations considering the accident of Fukushima Dai-ichi and Dai-ni
NPSs in 2011 was issued and handed to each electric power company and
the relevant organization.
㋪In order to strengthen the system to assist the nuclear accident suffers, the
"Team to Assist the Lives of the Nuclear Accident Sufferer" headed by the
Minister of Economy, Trade and Industry was established.

...

http://www.nisa.meti.go.jp/english/files/en20110331-2-1.pdf
 