Posted by Abdoulaye Bah
?conomie
Ebola: a government delegation to Kal?ta to reassure Chinese
Strong government delegation led by the Minister of Energy, Idrissa Thiam, on Friday visited the site of the hydroelectric dam Kaleta, located halfway between Dubr?ka, Fria and T?lim?l?. Officially, to visit the works and install a cordon sanitaire against the advance of hemorrhagic fever, did we found there.
Besides the Minister Idrissa Thiam and his relatives, the official delegation included the Secretary General of the Ministry of Budget, Andr? Louah, the National Director of Environment, Alex Louah and general manager Kal?ta project Cheikh Sylla Talib.
The visit comes following that of the Minister of Health, Remy Lamah, who had gone there to raise awareness, explain the spread of the virus and announce hygiene measures.
In recent days, the population of Kal?ta were under psychosis with the announcement of a possible massive departure of Chinese partners, because of the spread of the epidemic. Especially, as cases have been reported near, first in neighboring T?lim?l? and Dubr?ka nearby.
To reassure partners, the Ministry of Energy and the overall project strengthened the safe and sanitary system on site to meet the deadline set agenda.
Before the meeting to local populations strongly mobilized, officials found the installation of three sanitary cordons at three point, one at two kilometers from the village, the second to the main entrance of Kal?ta and the third to the main entry of the site. Everywhere, passersby are forced to make hand washing before crossing..
In his speech, the Director General of the project, Taliby Cheick Sylla, assured. "Today we are faced with a disease that starts creating psychosis in the city when, in reality, this is not the case. Therefore, in accordance with your instructions, we have created a cordon around Kal?ta to reassure our Chinese 'friends,' he says.
For Taliby Sylla, this cordon was put in place since six months, relation with the Ministry of Health. "The project put more than 150 million Guinean francs to buy the kits, educate, mobilize, to avoid problems. Standby team here since last March distributes soap and chlorinated water to villagers and Chinese employees . Today it is strengthened with the visit of the Minister of Energy for its support. "
For his part, Minister of Energy, Idrissa Thiam, praised the dam Kal?ta.
"While we're trying to achieve these important works, there is the disease Ebola hemorrhagic fever, which broke out in West Africa, reaching the Guinea.
Justifying the reasons for his visit to Kaleta, Mr. Thiam announced a dual purpose. "I came to do a site visit but also to get the government's message to the local population surrounding the project Kaleta and Kaleta also employees, Guinea as Chinese. Government will make every effort to ensure that the disease is receding and disappear in Guinea. The disease does not exist here even if there has been reported case not far. It does not exist in your area, on the whole perimeter Tondon and Labaya. "
Continuing, the Minister of Energy has also promised to put all security cordons and health needed to oust Ebola far of the perimeter of Kaleta. "This will be done in several ways, by educating the people living nearby.
Then putting a monitoring system like the one built at the airport in Conakry for entry."
In response, the spokesman of Chinese partners, Zhang Jun, welcomed the visit of the official delegation to discuss the measures taken. "Today, with the arrival of Ebola, we know that the government has taken tough measures. As an entrepreneur, today, we are here, Kaleta is a project where there are numerous personal. So how to protect the project? It is to protect personnel. This could guarantee the realization of the project.
We thank the delegation to build confidence to enhance the work. "
After the visits, the official delegation offered kits to staff and local people.
http://guineenews.org/ebola-une-delegation-gouvernementale-a-kaleta-pour-rassurer-les-chinois/
-------------------------------------------------------------------------------------
More about this project:
Translation Google
Sat August 16 2014, 7:04 p.m.
Posted By Amara Camara
?conomie
Kaleta project: the work done at 75 percent, says Taliby Sylla.
Begun April 4, 2012, development work on the hydroelectric dam Kal?ta advancing very rapidly. That is at least the observation that just made the managing director of the project, Taliby Cheick Sylla.
According to his statement, the state of overall progress of work is now at 75 percent. A level progress that allows him to confirm the official launch date of the first turbines of the dam, scheduled for 31 May, 2015.
According to him, all the essential equipments are already there and the first unit of the turbine and alternator should no longer delay to be received at the port of Conakry. Taliby Sylla explains that on the site of Kaleta, activities are not global but sectoral.
There are some who make the dam, there are others who work on the plant and in China, there is also manufacturing, says the CEO of Kaleta Project who maintains that the port of the dam is completed one hundred percent. As for the evacuator hole, he adds, it is 45 percent and the remaining piece will be made from starting in November.
'When we speak of the access road, the opening is one hundred percent. Manufacturing is one hundred percent, but all is not yet arrived in Conakry. A first unit of the turbine and alternator will be at te port of Conakry. We want to show them to the population for the poeple to be more reassured that essential equipment is on site and the time we have promoted, May 31, 2015, will be held. So putting it all together, we can say that we are at 75 percent of work progresses, '' says, Taliby Sylla very confident.
For a production capacity estimated at 240mW, Kaleta is the energy flagship project of President Alpha Cond? whose first turbines should start spinning starting end of May 2015 . It will probably be the largest hydroelectric dam ever built in the history of the Guinea.
Carried out by the Chinese company China Water Energy (CWE) for $ 526 million, 30 percent of the production of the Kaleta dam will go to neighboring countries as part of the sub-regional interconnection project.
http://guineenews.org/projet-kaleta-les-travaux-executes-a-75-pour-cent-affirme-taliby-sylla/
Sat, 23 Aug 2014, 18:06
Posted by Abdoulaye Bah
?conomie
Ebola: a government delegation to Kal?ta to reassure Chinese
Strong government delegation led by the Minister of Energy, Idrissa Thiam, on Friday visited the site of the hydroelectric dam Kaleta, located halfway between Dubr?ka, Fria and T?lim?l?. Officially, to visit the works and install a cordon sanitaire against the advance of hemorrhagic fever, did we found there.
Besides the Minister Idrissa Thiam and his relatives, the official delegation included the Secretary General of the Ministry of Budget, Andr? Louah, the National Director of Environment, Alex Louah and general manager Kal?ta project Cheikh Sylla Talib.
The visit comes following that of the Minister of Health, Remy Lamah, who had gone there to raise awareness, explain the spread of the virus and announce hygiene measures.
In recent days, the population of Kal?ta were under psychosis with the announcement of a possible massive departure of Chinese partners, because of the spread of the epidemic. Especially, as cases have been reported near, first in neighboring T?lim?l? and Dubr?ka nearby.
To reassure partners, the Ministry of Energy and the overall project strengthened the safe and sanitary system on site to meet the deadline set agenda.
Before the meeting to local populations strongly mobilized, officials found the installation of three sanitary cordons at three point, one at two kilometers from the village, the second to the main entrance of Kal?ta and the third to the main entry of the site. Everywhere, passersby are forced to make hand washing before crossing..
In his speech, the Director General of the project, Taliby Cheick Sylla, assured. "Today we are faced with a disease that starts creating psychosis in the city when, in reality, this is not the case. Therefore, in accordance with your instructions, we have created a cordon around Kal?ta to reassure our Chinese 'friends,' he says.
For Taliby Sylla, this cordon was put in place since six months, relation with the Ministry of Health. "The project put more than 150 million Guinean francs to buy the kits, educate, mobilize, to avoid problems. Standby team here since last March distributes soap and chlorinated water to villagers and Chinese employees . Today it is strengthened with the visit of the Minister of Energy for its support. "
For his part, Minister of Energy, Idrissa Thiam, praised the dam Kal?ta.
"While we're trying to achieve these important works, there is the disease Ebola hemorrhagic fever, which broke out in West Africa, reaching the Guinea.
Justifying the reasons for his visit to Kaleta, Mr. Thiam announced a dual purpose. "I came to do a site visit but also to get the government's message to the local population surrounding the project Kaleta and Kaleta also employees, Guinea as Chinese. Government will make every effort to ensure that the disease is receding and disappear in Guinea. The disease does not exist here even if there has been reported case not far. It does not exist in your area, on the whole perimeter Tondon and Labaya. "
Continuing, the Minister of Energy has also promised to put all security cordons and health needed to oust Ebola far of the perimeter of Kaleta. "This will be done in several ways, by educating the people living nearby.
Then putting a monitoring system like the one built at the airport in Conakry for entry."
In response, the spokesman of Chinese partners, Zhang Jun, welcomed the visit of the official delegation to discuss the measures taken. "Today, with the arrival of Ebola, we know that the government has taken tough measures. As an entrepreneur, today, we are here, Kaleta is a project where there are numerous personal. So how to protect the project? It is to protect personnel. This could guarantee the realization of the project.
We thank the delegation to build confidence to enhance the work. "
After the visits, the official delegation offered kits to staff and local people.
http://guineenews.org/ebola-une-delegation-gouvernementale-a-kaleta-pour-rassurer-les-chinois/
-------------------------------------------------------------------------------------
More about this project:
Translation Google
Sat August 16 2014, 7:04 p.m.
Posted By Amara Camara
?conomie
Kaleta project: the work done at 75 percent, says Taliby Sylla.
Begun April 4, 2012, development work on the hydroelectric dam Kal?ta advancing very rapidly. That is at least the observation that just made the managing director of the project, Taliby Cheick Sylla.
According to his statement, the state of overall progress of work is now at 75 percent. A level progress that allows him to confirm the official launch date of the first turbines of the dam, scheduled for 31 May, 2015.
According to him, all the essential equipments are already there and the first unit of the turbine and alternator should no longer delay to be received at the port of Conakry. Taliby Sylla explains that on the site of Kaleta, activities are not global but sectoral.
There are some who make the dam, there are others who work on the plant and in China, there is also manufacturing, says the CEO of Kaleta Project who maintains that the port of the dam is completed one hundred percent. As for the evacuator hole, he adds, it is 45 percent and the remaining piece will be made from starting in November.
'When we speak of the access road, the opening is one hundred percent. Manufacturing is one hundred percent, but all is not yet arrived in Conakry. A first unit of the turbine and alternator will be at te port of Conakry. We want to show them to the population for the poeple to be more reassured that essential equipment is on site and the time we have promoted, May 31, 2015, will be held. So putting it all together, we can say that we are at 75 percent of work progresses, '' says, Taliby Sylla very confident.
For a production capacity estimated at 240mW, Kaleta is the energy flagship project of President Alpha Cond? whose first turbines should start spinning starting end of May 2015 . It will probably be the largest hydroelectric dam ever built in the history of the Guinea.
Carried out by the Chinese company China Water Energy (CWE) for $ 526 million, 30 percent of the production of the Kaleta dam will go to neighboring countries as part of the sub-regional interconnection project.
http://guineenews.org/projet-kaleta-les-travaux-executes-a-75-pour-cent-affirme-taliby-sylla/